Clarksburg, CA

Project is 275,000 square feet of Bogle a new wine processing facility consisting of a crushing and bottling plant, barrel storage for 5.9 million gallons, and enough room to store 200,000 cases of wine. Administrative and maintenance space included, along with a stainless steel “tank farm” that will hold 4.5 million gallons of wine. Bogle vintners will process all of their grapes here. Bogle will also contract with other wineries for the processing and storage of their grapes.

Concrete work consisted of: foundations, slab on grade with reinforcing, cast-in-place walls, tank farm pedestals, curbs and related site work. Concrete Services placed and finished nearly 400,000 square feet of slab on grade and paving concrete, and pouring over 16,700 cubic yards on the project.

Architect: Summit Engineering, Inc
General Contractor: Rudolph & Sletten